The S.R. 29 PD&E Study began on December 4, 2007. The data collection and development of the widening alternatives are underway. The PD&E Study is anticipated to be complete in the summer of 2010.

A public information workshop was held in the fall of 2008 and a public hearing is scheduled for spring of 2010. After the public hearing, the project documents will be submitted to the Federal Highway Administration for Location and Design Concept Acceptance.

There is currently no funding in FDOT's five year work program for design, right of way acquisition or construction.